Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer:
Explanation:
Work station Time Transfer time
1 40
2 52 30
3 43 30
4 48 30
5 30 30
6 65 30
7 53 30
8 49 30
380 210
The cycle time of the line = 65 seconds which is the maximum of all the times
The time to process one work unit = 380 + 210 = 590 secounds
The average production rate = 60/57 = 0.92 Pc/min
Time to produce 10000 units = 10000*0.92 = 9200 Min
= 153 hrs
= 153/8
= 19.125 days
a) The cycle time for the flow line = 590 seconds or 9.833 minutes (590/60).
b) The time to process one work unit = 590 seconds
c) The average production rate at each station = 73.75 seconds (590/8).
d) The time to produce 100,000 units = 983,300 minutes (100,000 units x 9.833 minutes).
Data and calculations:
Workstation Time Transfer time Total Time
Taken from each Station Per Station
1 40 30 70 (40 + 30)
2 52 30 82 (52 + 30)
3 43 30 73 (43 + 30)
4 48 30 78 (48 + 30)
5 30 30 60 (30 + 30)
6 65 30 95 (65 + 30)
7 53 30 83 (53 + 30)
8 49 0 49 (49 + 0)
Total time 380 210 590
Thus, the cycle time is determined as the average time between the completion of units, which is 9.833 minutes.
Learn more about cycle time and average production rate here: https://brainly.com/question/20533888
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.