At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Our platform provides a seamless experience for finding reliable answers from a knowledgeable network of professionals. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

DriveTrain, Inc. instituted a new process in October 2020. During October, 13,800 units were started in Department A. Of the units started, 8,950 were transferred to Department B, and 4,850 remained in Work-in-Process at October 31, 2020. The Work-in-Process at October 31, 2020, was 100% complete as to material costs and 50% complete as to conversion costs. Material costs of $37,260 and conversion costs of $45,500 were charged to Department A in October. What were the total costs transferred to Department B assuming Department A uses weighted-average process costing

Sagot :

Zviko

Answer:

$59,965

Explanation:

Equivalent Units

Materials = 8,950 x 100 % + 4,850 x 100 % = 13,800 units

Conversion Costs = 8,950 x 100 % + 4,850 x 50 % = 11,375 units

Total Costs

Materials = $37,260

Conversion Costs = $45,500

Cost per Equivalent unit

Materials = $37,260 / 13,800 units = $2.70

Conversion Costs = $45,500/ 11,375 units  = $4.00

Total Unit Cost = $2.70 + $4.00 = $6.70

Total costs transferred to Department B

Total costs = 8,950 x $6.70 = $59,965

Therefore, the total costs transferred to Department B is $59,965

Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.