Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Connect with a community of experts ready to provide precise solutions to your questions on our user-friendly Q&A platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

Consider the simple 3-station assembly line illustrated below, where the 2 machines at Station 1 are parallel, i.e., the product only needs to go through one of the 2 machines before proceeding to Station 2. Station 1 Machine A has a capacity of 3 units per hour; Station 1 Machine B has a capacity of 3 units per hour; Station 2 has a capacity of 5 units per hour; Station 3 has a capacity of 10 units per hour What is the bottleneck time of this process

Sagot :

Answer:

The bottleneck time for this process is 20 minutes.

Explanation:

a) Data and Calculations:

Station  Capacity per hour  Time required per unit

1 A               3                          20 minutes (60/3)

1 B               3                          20 minutes (60/3)

2                  5                          12 minutes (60/5)

3                 10                           6 minutes (60/10)

Total demand for the process = 38 minutes (20+12+6)

b) The bottleneck is the station that requires the longest time for its outputs to be processed.  The bottleneck in this process is given by Station One, requiring 20 minutes to meet output requirements through either machine A or machine B.  The bottleneck constitutes a constraint on the process capacity to achieve results.

We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.