Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Get expert answers to your questions quickly and accurately from our dedicated community of professionals. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer:
The bottleneck time for this process is 20 minutes.
Explanation:
a) Data and Calculations:
Station Capacity per hour Time required per unit
1 A 3 20 minutes (60/3)
1 B 3 20 minutes (60/3)
2 5 12 minutes (60/5)
3 10 6 minutes (60/10)
Total demand for the process = 38 minutes (20+12+6)
b) The bottleneck is the station that requires the longest time for its outputs to be processed. The bottleneck in this process is given by Station One, requiring 20 minutes to meet output requirements through either machine A or machine B. The bottleneck constitutes a constraint on the process capacity to achieve results.
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.