Get the answers you need at Westonci.ca, where our expert community is always ready to help with accurate information. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

In this simulation, theoretical utilization of the intensive care unit (ICU) is calculated as the flow rate of patients that arrive for service at the ICU in a given unit of time divided by the ICU’s capacity to serve customers in that same unit of time. You can think about this as demand/capacity. What is the theoretical utilization of the ICU if the mean inter-arrival time is 4 hour(s), the mean length of stay is 6 hour(s), and there are 4 beds in the ICU?

Sagot :

Answer:

The theoretical utilization of the ICU is:

= 0.25 or 25%

Explanation:

Inter-arrival time or flow rate of patients that arrive for service at the ICU = 4 hours

Mean length of stay = 6 hours

ICU's capacity to serve customers in 6 hours = 4*6 = 24 bed-hours

Total demand = 6 hours

Therefore, the theoretical utilization = flow rate of patients that arrive for service at the ICU in a given unit of time divided by ICU's capacity to serve customers in that same unit of time

= 6 hours/24 bed-hours

= 0.25

Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.