Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer:
Results are below.
Explanation:
Giving the following information:
Total unitary variable cost= $16.5
Total fixed costs= $116,000
Now, the flexible budget for each production level:
16,000 units:
Total variable cost= 16.5*16,000= 264,000
Total fixed cost= 116,000
Total costs= $380,000
18,000 units:
Total variable cost= 16.5*18,000= 297,000
Total fixed cost= 116,000
Total costs= $413,000
20,000 units:
Total variable cost= 16.5*20,000= 330,000
Total fixed cost= 116,000
Total costs= $446,000
Thanks for using our platform. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.