At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer:
Part A answer: 10 2/3 months
Part B answer: No
Step-by-step explanation:
Using what we gathered from the word problem, and the hint, we know that y = distance, x = time, and b = 3200.
3200 is the total number of ft meant for the hole to be dug. If we've been digging for 5 months, and we have 1700 ft yet to be dug, then after 5 months we have dug (3200 - 1700 =) 1500 ft in 5 months.
-1500 ft/5 months = 300 ft/month
-Digging the final 1700 ft will take 5 2/3 months
^ Using this information, we know that the total number of months it takes to dig the entirety of the tunnel is 10 2/3
In the second part of the problem, we're asked to determine whether or not a deadline of August 2021 was enough time to complete the 10 2/3 month-long project if the digging began in December of 2020.
If said project commenced in December 2020, and the deadline was August 2021, then there would be 1, 2, 3, 4, 5, 6, 7, 8... Roughly 8 1/2 months to complete the tunnel. 10 2/3 months is > (greater than) 8 1/2 months. So, no. That start-to-finish deadline would not be enough time.
Good luck!!
Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.