Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

Trek Company has the following production data for April: units transferred out 40,200, and ending work in process 6,220 units that are 100% complete for materials and 40% complete for conversion costs. If unit materials cost is $4 and unit conversion cost is $10. Determine the costs to be assigned to the units transferred out and the units in ending work in process.

Sagot :

Answer:

the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively

Explanation:

The computation is shown below:

Cost assign to units transferred out is

= 40,200 units × $4 + 40,200  units ×  $10

= $160,800 + $402,000

= $562,800

And, the Cost assign to work in progress is

= 6,220  units × $4 + (6,220 units × 0.40) × $10

= $24,880 + $24,880

= $49,760

Hence, the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively