Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Find reliable answers to your questions from a wide community of knowledgeable experts on our user-friendly Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Identify the term being described for each of the following: A - sequence of activities in a project. B - The longest time sequence of activities in a project C - Used when two activities have the same starting and finishing points. D - The difference in time length of any path and the critical path. E - The statistical distribution used to describe variability of an activity time. F - The statistical distribution used to describe path variability an activity by allocating additional resources.

Sagot :

Answer: See explanation

Explanation:

A - sequence of activities in a project. = A path

B - The longest time sequence of activities in a project = Critical path

C - Used when two activities have the same starting and finishing points. = Critical activity

D - The difference in time length of any path and the critical path. = The path slack

E - The statistical distribution used to describe variability of an activity time. = Beta distribution.

F - The statistical distribution used to describe path variability an activity by allocating additional resources. = Normal distribution