Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Find reliable answers to your questions from a wide community of knowledgeable experts on our user-friendly Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Answer: See explanation
Explanation:
A - sequence of activities in a project. = A path
B - The longest time sequence of activities in a project = Critical path
C - Used when two activities have the same starting and finishing points. = Critical activity
D - The difference in time length of any path and the critical path. = The path slack
E - The statistical distribution used to describe variability of an activity time. = Beta distribution.
F - The statistical distribution used to describe path variability an activity by allocating additional resources. = Normal distribution
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.