Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Discover comprehensive answers to your questions from knowledgeable professionals on our user-friendly platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

ob 412 was one of the many jobs started and completed during the year. The job required $9,700 in direct materials and 45 hours of direct labor time at a total direct labor cost of $10,600. If the job contained four units and the company billed at 65% above the unit product cost on the job cost sheet, what price per unit would have been charged to the customer

Sagot :

Answer:

the price per unit that should be charged to the customer is $8,373.75

Explanation:

The computation of the price per unit that should be charged to the customer is shown below

Unit product cost = ($9,700 + $10,600) ÷ 4 units

= $5,075 per unit

Now the price per unit is

= Unit product cost × given percentage

= $5,075 × 165%

= $8,373.75