Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer:
Variable overhead efficiency variance = $8,600 favorable
Explanation:
Variable overhead efficiency variance is the difference between the actual time taken to achieve a given production output less the standard hours for same multiplied by the standard variable overhead rate
Variable overhead efficiency variance is determined as follows:
Hours
standard hours for actual output 16,800
Actual hours 14,800
Efficiency variance 2,000 favorable
× standard variable OH rate × $4.30
Variable overhead efficiency variance ($) $8,600 favorable
Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.