Looking for reliable answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Discover reliable solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
Answer:
Results are below.
Explanation:
To calculate the direct material rate and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (0.55 - 0.54)*4,000
Direct material price variance= $40 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (0.75*4,800 - 3,588)*0.55
Direct material quantity variance= $6.6 favorable
Finally, the total variance:
Total direct material variance= 40 + 6.6= $46.6 favorable
Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.