At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Get detailed and accurate answers to your questions from a community of experts on our comprehensive Q&A platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer:
Results are below.
Explanation:
To calculate the direct material rate and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (0.55 - 0.54)*4,000
Direct material price variance= $40 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (0.75*4,800 - 3,588)*0.55
Direct material quantity variance= $6.6 favorable
Finally, the total variance:
Total direct material variance= 40 + 6.6= $46.6 favorable
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.