Explore Westonci.ca, the top Q&A platform where your questions are answered by professionals and enthusiasts alike. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Some project managers prefer the PERT chart over the Gantt chart because it clearly illustrates task dependencies. A PERT chart, however, can be much more difficult to interpret, especially on complex projects. Alternatively, some project managers may choose to use both techniques. If you are the project manager of a residential construction project, will you prefer PERT chart to Gantt chart? Explain why?

Sagot :

Answer:

PERT Chart and GANTT Chart

As the project manager of a residential construction project, I will prefer the PERT chart to the GANTT chart because a PERT chart displays task dependencies unlike a Gantt chart.  With the PERT chart, the sequence of tasks is clearly mapped out.  Dependent tasks are carried out when other tasks that they depend on have been executed.

Explanation:

By definition, a Gantt chart is like a bar chart that lays out project tasks and timelines using bars.  On the other hand, a PERT chart follows a structure in the form of flow charts or network diagrams.  It displays all the project tasks in separate boxes.  The boxes are then connected with arrows which clearly show the task dependencies.

We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Get the answers you need at Westonci.ca. Stay informed by returning for our latest expert advice.