Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Get quick and reliable solutions to your questions from a community of experienced professionals on our platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer:
Answer:
Amount of overhead applied is $270
correct option is (a) $270
Explanation:
given data
overhead cost = $105,000
overheat rate = $3 per machine hour
manufacturing overhead = 70000 machine hour
required = 60 machine hours
to find out
The amount of overhead applied to Job P 233 is closest to
solution
we find manufacturing overhead rate here that is
manufacturing overhead rate =
put here value
manufacturing overhead rate =
manufacturing overhead rate = 1.5 per machine hour
and
Total manufacturing overhead rate will be for overheat rate $3
Total manufacturing overhead rate = (3 + 1.5) = $4.5 per machine hour
so we can say that Amount of overhead is job P 233 is
Amount of overhead applied = 60 × $4.5 = 270
so here correct option is (a) $270
Explanation:
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.