Discover a wealth of knowledge at Westonci.ca, where experts provide answers to your most pressing questions. Get immediate and reliable solutions to your questions from a community of experienced experts on our Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer:
Cherokee Manufacturing Company
a. Sales volume variance is:
= $2,400 F
b. Variable cost volume variance is:
= $1,440 U
c. Fixed cost in the flexible budget = $4,800
d. Fixed cost per unit:
1. Planned activity = $2.40
2. Actual activity = $2.18
Explanation:
a) Data and Calculations:
Standard price and cost data:
Sales price $ 12.00 per unit
Variable manufacturing cost $ 7.20 per unit
Fixed manufacturing cost $ 3,600 total
Fixed selling and administrative cost $ 1,200 total
Planned production and sales = 2,000 units
Actual production and sales = 2,200 units
Sales volume variance = Actual sales - Standard sales multiplied by Standard price
= 2,200 - 2,000 * $12
= 200 * $12
= $2,400 F
Variable cost volume = Actual production - Standard production multiplied by Standard Variable Cost
= 200 * $7.20
= $1,440 U
Flexible fixed costs:
Fixed manufacturing cost = $ 3,600 total
Fixed selling and administrative cost = $ 1,200 total
Total fixed costs = $4,800
Fixed cost per unit:
Planned activity = $2.40 ($4,800/2,000)
Actual activity = $2.18 ($4,800/2,200)
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.