At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

In 1951, a small approach embankment was constructed for a highway bridge over a river south of Los Angeles. The embankment was underlain by 5 ft of organic clay. Records of the settlement rate indicate that 90% of the consolidation settlements occurred in the first 4.5 years after construction. A new bridge over the river is now planned for a site a few hundred yards from the old bridge. The approach embankment to the new bridge will be underlain by 20 ft of the same organic clay found at the old bridge site. Estimate the time required to achieve an average degree of consolidation of 90% under the new embankment. Assume single drainage from the organic clay at both sites..

Sagot :

Answer:

72 years

Explanation:

The degree of consideration is the same for both bridges = 90%

Height  of first highway bridge( d1 ) = 5 ft

Time to consolidation ( t1 )= 4.5 years

Height of second bridge ( d2 ) = 20 ft

Time to consolidation ( t2 ) = ?

we will apply this relation below

Tv = Cv * t / d^v

Tv = constant

for a single drainage condition : t ∝ d^v hence; d = H

∴ [tex]\frac{t_{2} }{t_{1} } = (\frac{d_{2} }{d_{1} })[/tex]^2

t2 = t1 ( d2/d1 )^2

   = 4.5 ( 20 / 5 )^2

  = 72 years