Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.
Sagot :
Answer:
The appropriate answer is "$8,457,50".
Explanation:
The given values are:
Direct material cost,
= $9,500
Direct labor cost,
= $10,400
Units completed in job 412,
= 4
Now,
The total cost for completion of job 412 will be:
= [tex]Direct \ materials \ cost + Direct \ labor \ costs[/tex]
On substituting the values, we get
= [tex]9,500 + 10,400[/tex]
= [tex]19,900[/tex] ($)
Unit produced cost will be:
= [tex]\frac{19,900}{4}[/tex]
= [tex]4,975[/tex] ($)
70% of unit produced cost will be the profit margin, then
= [tex]70 \ percent\times 4,975[/tex]
= [tex]3,482.50[/tex] ($)
hence,
The price charged to the customer will be:
= [tex]Unit \ product \ cost + Profit \ margin[/tex]
On substituting the values, we get
= [tex]4,975 + 3,482.50[/tex]
= [tex]8,457,50[/tex] ($)
We appreciate your time on our site. Don't hesitate to return whenever you have more questions or need further clarification. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.