Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Experience the convenience of getting accurate answers to your questions from a dedicated community of professionals. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
The appropriate answer is "$8,457,50".
Explanation:
The given values are:
Direct material cost,
= $9,500
Direct labor cost,
= $10,400
Units completed in job 412,
= 4
Now,
The total cost for completion of job 412 will be:
= [tex]Direct \ materials \ cost + Direct \ labor \ costs[/tex]
On substituting the values, we get
= [tex]9,500 + 10,400[/tex]
= [tex]19,900[/tex] ($)
Unit produced cost will be:
= [tex]\frac{19,900}{4}[/tex]
= [tex]4,975[/tex] ($)
70% of unit produced cost will be the profit margin, then
= [tex]70 \ percent\times 4,975[/tex]
= [tex]3,482.50[/tex] ($)
hence,
The price charged to the customer will be:
= [tex]Unit \ product \ cost + Profit \ margin[/tex]
On substituting the values, we get
= [tex]4,975 + 3,482.50[/tex]
= [tex]8,457,50[/tex] ($)
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.