At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Discover precise answers to your questions from a wide range of experts on our user-friendly Q&A platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.
Sagot :
Answer:
Storm Tools
STORM TOOLS
1. Sales Budget
For the Three Months January to March
January February March
Expected Cash Collections
From Sales $1,400,000 $2,275,000 $2,500,000
STORM TOOLS
2. Production Budget
For the Three Months January to March
January February March
Production Schedule 25,000 27,500 30,000
Cost of direct materials $1,000,000 $1,100,000 $1,200,000
STORM TOOLS
4. Direct Materials Budget
For the Three Months January to March
January February March
Expected Cash Payments
for Materials Purchases $1,025,000 $1,125,000
STORM TOOLS
5. Direct Labor Budget
For the Three Months January to March
January February March
Direct labor costs $200,000 $220,000 $240,000
STORM TOOLS
6. Factory Overhead Budget
For the Three Months January to March
January February March
Variable overhead $75,000 $82,500 $90,000 $97,500
Fixed overhead 25,000 25,000 25,000 25,000
Total overhead $100,000 $107,500 $115,000 $122,500
Depreciation cost 15,000 15,000 15,000 15,000
Cash payment for o/h $85,000 $92,500 $100,000 $107,500
STORM TOOLS
7. Ending Finished Goods Inventory
31-Mar
Units Per Unit Cost Per Unit Total
January 5,000 $51.91 $259,550
February 7,500 $51.91 $389,325
March 12,500 $51.91 $648,875
STORM TOOLS
Selling, General, and Administrative Budget
For the Three Months January to March
January February March
Fixed overhead:
Salaries $100,000 $100,000 $100,000
Office expenses 40,000 40,000 40,000
Advertising 75,000 75,000 75,000
Fixed overhead $215,000 $215,000 $215,00
Variable overhead 210,000 341,250 375,000
Selling, General, and Admin. $425,000 $556,250 $590,000
STORM TOOLS
Cash Budget
For the Three Months January to March
January February March
Beginning cash balance $500,000 $1,135,000 $1,461,500
Plus: Customer receipts 1,400,000 2,275,000 2,500,000
Available cash $1,900,000 $3,410,000 $3,961,500
Less disbursements:
Direct materials $0 $1,025,000 $1,125,000
Direct labor 200,000 220,000 240,000
Factory overhead 85,000 92,500 100,000
SG&A 425,000 556,250 590,000
Total disbursements $710,000 $1,893,750 $2,055,000
Cash surplus/(deficit) $1,190,000 $1,516,250 $1,906,500
Financing:
Planned repayment $50,000 $50,000 $50,000
Interest on note
(1/2% of unpaid balance) 5,000 4,750 4,500
Ending cash balance $1,135,000 $1,461,500 $1,852,000
Explanation:
a) Data and Calculations:
Initial Balance Sheet on January 1:
Cash $500,000
Plant and equipment $2,500,000
Total assets $3,000,000
Notes payable $1,000,000
Residual equity $2,000,000
Total liabilities and equity $3,000,000
Repayment of note:
Note payment $50,000 per month
Accrued interest 250
Total repayment $50,250 per month
January February March April
Production Schedule 25,000 27,500 30,000 32,500
Cost of direct materials $1,000,000 $1,100,000 $1,200,000 $1,300,000
Ending raw materials 6,875 7,500 8,125
Production Schedule 25,000 27,500 30,000 32,500
Beginning raw materials 6,250 6,875 7,500 8,125
Purchase of materials 25,625 28,125 30,625
Cost price = $40 per drill
Payment for materials $1,025,000 $1,125,000 $1,225,000
Beginning Finished goods 5,000 7,500 12,500
Production 25,000 27,500 30,000 32,500
Ending Finished goods 5,000 7,500 12,500 15,000
Sales 20,000 25,000 25,000 30,000
Selling price = $100 per drill
Credit sales: $1,000,000 $1,250,000 $1,250,000 $1,500,000
40% month of sale 400,000 625,000 625,000 750,000
60% following month 400,000 625,000 625,000
Cash sales 1,000,000 1,250,000 1,250,000 1,500,000
Total sales collection $1,400,000 $2,275,000 $2,500,000 $2,875,000
Direct labor per drill = 20 minutes
Labor rates = $24 per hour
Variable overhead = $9 per direct labor hour
Production Schedule 25,000 27,500 30,000 32,500
Total labor hours 8,333 9,167 10,000 10,833
Direct labor costs $200,000 $220,000 $240,000 $260,000
Variable overhead $75,000 $82,500 $90,000 $97,500
Fixed overhead 25,000 25,000 25,000 25,000
Total overhead $100,000 $107,500 $115,000 $122,500
Depreciation cost 15,000 15,000 15,000 15,000
Cash payment for o/h $85,000 $92,500 $100,000 $107,500
Selling, general, and administrative costs:
Fixed overhead $215,000 $215,000 $215,000 $215,000
Variable overhead 210,000 341,250 375,000 431,250
Total selling, etc $425,000 $556,250 $590,000 $628,250
Cost of production:
Cost of direct materials $1,000,000 $1,100,000 $1,200,000 $1,300,000
Direct labor costs $200,000 $220,000 $240,000 $260,000
Overhead applied 97,746 107,529 117,300 127,071
Total costs of prodn. $1,297,746 $1,427,529 $1,557,300 $1,687,071
Production Schedule 25,000 27,500 30,000 32,500
Cost per unit $51.91 $51.91 $51.91 $51.91
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.