Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Our platform provides a seamless experience for finding reliable answers from a knowledgeable network of professionals. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer:
The indifference point is 106,457 units.
Explanation:
Giving the following information:
Process A:
Fixed cost= $1,430,000
Variable cost= $14.32 per metal panel.
Process B:
Fixed cost= $820,000
Variable cost= $20.05 per metal panel.
To calculate the indifference point between two processes, first, we need to formulate the total cost equation for each process:
Process A:
Total cost= 1,430,000 + 14.32*x
Process B:
Total cost= 820,000 + 20.05*x
x= number of units
Now, we need to equal both formulas and isolate x:
1,430,000 + 14.32x = 820,000 + 20.05x
610,000 = 5.73x
x= 106,457
The indifference point is 106,457 units.
We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.