Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Discover a wealth of knowledge from experts across different disciplines on our comprehensive Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

Polson Pool Company is involved in a number of competitive bidding situations. The following costs are anticipated for a project to be bid for Terrance Manufacturing:
Direct material $ 680,000
Direct labor 2,450,000
Allocated variable overhead 570,000
Allocated fixed cost 230,000
Which of these costs would be treated differently if Polson had either excess capacity or no excess capacity?
a. Allocated variable overhead, $570,000
b. Direct labor, $2,450,000
c. Allocated fixed cost, $230,000
d. Direct materials used, $680,000.


Sagot :

Answer: c. Allocated fixed cost, $230,000

Explanation:

The Allocated fixed cost is fixed based on a certain level of production. If Polson had excess capacity to produce more goods or no excess capacity, the allocated fixed costs would have to be treated differently to account for this.

The variable costs however would not have to change because they are already based on the quantity of goods produced so even if there is excess or no excess capacity, their cost per unit would not change.