Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Join our Q&A platform and get accurate answers to all your questions from professionals across multiple disciplines. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: Activity Cost Driver Amount M XY Production setups Number of setups $82,000 8 12 Material handling Number of parts 48,000 56 24 Packaging costs Number of units 130,000 80,000 50,000 $260,000 What is the total overhead per unit allocated to Product M using activity-based costing (ABC)

Sagot :

Answer:

Unitary cost= $1.83

Explanation:

First, we need to calculate the allocation rates:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Production setups= 82,000/20= $4,100 per setup

Material handling= 48,000/80= $600 per part  

Packaging costs= 130,000/130,000= $1 per unit

Now, we allocate cost to Product M:

Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base

Production setups= 4,100*8= 32,800

Material handling= 600*56= 33,600  

Packaging costs= 1*80,000= 80,000

Total= $146,400

Finally, the unitary cost:

Unitary cost= 146,400 / 80,000

Unitary cost= $1.83