Westonci.ca is the premier destination for reliable answers to your questions, brought to you by a community of experts. Our Q&A platform provides quick and trustworthy answers to your questions from experienced professionals in different areas of expertise. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer: See explanation
Explanation:
From the information given,
Budgeted hours = 660
Budgeted rate per hour = 3.4
Budgeted rooms to clean = (600 × 60)/36 = 36000/36 = 1000
1. What is the amount of the budget variance?
This will be:
= (Actual room - Budgeted room) × Standard rate
= (1050 - 1000) × 3.4
= 50 × 3.4
= 170 favorable
2. What is the amount of the volume variance?
This will be:
= Standard cost - Actual labor cost
= (630 × 3.4) - (660 × 3.3)
= 2142 - 2178
= 36 Unfavorable
3. What is the amount of the efficiency variance?
This will be:
= 3.4 × (630 - 660)
= 3.4 × (-30)
= 10.20 Unfavorable
4. What is the amount of the rate variance?
This will be:
= Actual time ( Standard rate - Actual rate)
= 660 × (3.4 - 3.3)
= 660 × 1
= 660 Favorable
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.