Westonci.ca is the ultimate Q&A platform, offering detailed and reliable answers from a knowledgeable community. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Answer:
Project X = $6,980.82
Project Y = - $2,478.42
Explanation:
The Present value is the price today of future cash flows and is calculated as follows :
Project X
($21,000) CF 0
$8,000 CF 1
$8,000 CF 2
$8,000 CF 3
$8,000 CF 4
$8,000 CF 5
$8,000 CF 6
I/YR = 18%
Therefore, NPV is $6,980.82
Project Y
($21,000) CF 0
$0 CF 1
$0 CF 2
$0 CF 3
$0 CF 4
$0 CF 5
$50,000 CF 6
I/YR = 18%
Therefore, NPV is - $2,478.42
Thank you for your visit. We are dedicated to helping you find the information you need, whenever you need it. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.