Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

The standard cost of direct labor per unit is calculated by:_______
A. multiplying the standard quantity of direct labor by the standard price of direct labor.
B. multiplying the actual quantity of direct labor by the standard price of direct labor.
C. dividing the standard quantity of direct labor by the standard price of direct labor.
D. adding the standard quantity of direct labor to the standard price of direct labor.


Sagot :

Answer:

A. multiplying the standard quantity of direct labor by the standard price of direct labor.

Explanation:

Standard cost of direct labor = Standard quantity*Standard price. Standard cost of direct labor per hour are calculated and compared with the Actual cost of direct labor per hour and multiplied by Actual hours used to calculate direct labor rate variance.

So, option A (multiplying the standard quantity of direct labor by the standard price of direct labor) is correct.

We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.