Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.
Sagot :
Answer:
b. . $160.50
Explanation:
Projected Sales 1,000 units
Desired ending inventory = 10%*1,000 = 100 units
Beginning Inventory = 30 units
Required production = Projected Sales + Desired ending inventory - Beginning Inventory
Required production = 1,000 units + (10%*1,000 units) - 30 units
Required production = 1,000 units + 100 units - 30 units
Required production = 1,070 units
Labor hours per unit = 0.20
Cost per labor hour = $0.75
Budgeted labor cost for March = Required production*Labor hours per unit*Cost per labor hour
Budgeted labor cost for March = 1,070 units*$0.20*$0.75
Budgeted labor cost for March = $160.50
Hence, the budgeted labor cost for March is $160.50.
Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.