Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Join our platform to connect with experts ready to provide precise answers to your questions in different areas. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

It takes 14 hours to seal a hardwood floor with varnish. If each coat requires 3

1/4 hours to dry,


how many coats are applied?


Sagot :

Answer:

4.3 coats

Step-by-step explanation:

if 1 coat takes 3 1/4 hours (same as 3.25 hours)

3.25 hours = 1 coat

14 hours = x coats

(cross multiply)

3.25 × x = 14 × 1

3.25x = 14

(divide both sides by 3.25)

x = 4.3

therefore, 4.3 coats are applied

hope this helps!

We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.