At Westonci.ca, we connect you with experts who provide detailed answers to your most pressing questions. Start exploring now! Get immediate and reliable solutions to your questions from a community of experienced experts on our Q&A platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

Math , pleaaaase

You are given the results of measurements of sizes of a crushed stone for road
construction. The technical requirement is the following: The mean size of the stones must be in the interval [33-36] mm and standard deviation must be smaller than 6 mm. Will this batch pass the technical control?


Math Pleaaaase You Are Given The Results Of Measurements Of Sizes Of A Crushed Stone For Road Construction The Technical Requirement Is The Following The Mean S class=

Sagot :

Answer:

The standard deviation is above 6 mm, which means that this batch does not pass the technical control.

Step-by-step explanation:

Mean of the batch:

The mean of the batch is the sum of all values divided by the number of items. So

[tex]M = \frac{31+32+38+34+45+41+24}{7} = 35[/tex]

Mean in the desired interval.

Standard deviation:

Square root of the sum of the difference squared between each term and the mean, divided by the number of itens. So

[tex]S = \sqrt{\frac{(31-35)^2+(32-35)^2+(38-35)^2+(34-35)^2+(45-35)^2+(41-35)^2+(24-35)^2}{7}} = 6.46[/tex]

The standard deviation is above 6 mm, which means that this batch does not pass the technical control.

We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.