Discover answers to your most pressing questions at Westonci.ca, the ultimate Q&A platform that connects you with expert solutions. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

If 10 workers, working for 4 hours complete the work in 12 days, in how many days will 8 workers working for 6 hours complete the same work?

Sagot :

Answer:

As per the question, 10 workers working for 4 hours a day complete their work = 12 days. 1 person working for 1 hour a day complete the work = 12×10×4 days. Thus, the 8 persons working for 6 hrs a day complete their work in 10 days.