Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer:
Variable overheads efficiency variance = $13,040 favorable
Explanation:
Variable overheads efficiency variance is the difference between the standard hours of actual output and actual hours valued at the standard variable overhead rate per hour
Hours
5,900munits should have taken (5,900× 0.9) 5,310
but did take 2050
efficiency variance in hours 3,260 favorable
Standard rate per hour $4.00
Variable overheads efficiency variance 13,040 favorable
Variable overheads efficiency variance = $13,040 favorable
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.