At Westonci.ca, we connect you with the best answers from a community of experienced and knowledgeable individuals. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
a. The costs can be classified as follows:
Prevention: Quality training
Appraisal: Product inspection and Material inspection
Internal Failure: Scrap and rework
External Failure: Product Warranty
b-1. We have:
Total quality cost as a percentage of sales for Year 1 = 1.60%
Total quality cost as a percentage of sales for Year 2 = 1.65%
b-2. Profit has increased by $295,000 because of quality improvements between Year 1 and Year 2.
Explanation:
a. Classify the costs as prevention, appraisal, internal failure, and external failure.
The costs can be classified as follows:
Prevention: Quality training
Appraisal: Product inspection and Material inspection
Internal Failure: Scrap and rework
External Failure: Product Warranty
b-1. Compute total quality cost as a percentage of sales for each of the two years.
Total quality cost as a percentage of sales = ((Product inspection + Material inspection) / Sales) * 100 ………………. (1)
Using equation (1), we have:
Total quality cost as a percentage of sales for Year 1 = (($100,000 + $60,000) / 10,000,000) * 100 = 1.60%
Total quality cost as a percentage of sales for Year 2 = (($125,000 + $40,000) / 10,000,000) * 100 = 1.65%
b-2. By how much has profit increased because of quality improvements between Year 1 and Year 2?
To calculate the profit associated to quality, only costs associated to quality are deducted from Sales as follows:
Profit associated to quality = Sales - Scrap - Rework - Product inspection - Materials inspection ……… (1)
Using equation (1), we have:
Profit associated to quality for Year 1 = $10,000,000 - $400,000 - $600,000 - $100,000 - $60,000 = $8,840,000
Profit associated to quality for Year 2 = $10,000,000 - $300,000 - $400,000 - $125,000 - $40,000 = $9,135,000
Therefore, we have:
Increase in profit because of quality improvements = Profit associated to quality for Year 2 - Profit associated to quality for Year 1 = $9,135,000 - $8,840,000 = $295,000
Therefore, profit has increased by $295,000 because of quality improvements between Year 1 and Year 2.
Thanks for using our platform. We're always here to provide accurate and up-to-date answers to all your queries. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.