Westonci.ca is your trusted source for finding answers to a wide range of questions, backed by a knowledgeable community. Get quick and reliable solutions to your questions from a community of experienced professionals on our platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer:
RF Electronics Company
The expected number of lost calls per hour are:
= zero.
Explanation:
a) Data and Calculations:
Number of sales department telephone lines = 3
Number of persons taking sales calls = 1
Average completed sales profit = $70
Average calls per hour over the last 6 months = 6
Time required by the sales rep to service a call and complete the sale = 3 minutes
Number of calls that the sales rep can service in 1 hour = 20 (60/3)
Expected number of lost calls = Average calls per hour minus number of calls that the sales rep can service per hour
= 6 - 20 = -14
This means that the sales rep has opportunity to answer 14 more calls within the hour but only 6 calls are received. Therefore, there are no lost calls.
We hope our answers were useful. Return anytime for more information and answers to any other questions you have. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.