Welcome to Westonci.ca, where you can find answers to all your questions from a community of experienced professionals. Ask your questions and receive accurate answers from professionals with extensive experience in various fields on our platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.
Sagot :
Answer:
$66.73
Explanation:
Activity Overhead Cost Activity Base Activity Rate
Engineering and Design $404,712 2,409 $168
Quality Control $269,808 12,848 $21
Machinery $539,616 33,726 $16
Miscellaneous Overhead $134,904 26,400 $5.11
High F
Activity Base-Usage Activity Rate Activity Cost
Engineering and Design 969 $168 $162,792
Quality Control 5,648 $21 $118,608
Machinery 20,286 $16 $324,576
Miscellaneous Overhead 20,286 $5.11 $61,320
Total Overhead cost $667,296
Produced units 10,000
Per unit overhead cost $66.73
Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.