Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Discover solutions to your questions from experienced professionals across multiple fields on our comprehensive Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

Marle Construction enters into a contract with a customer to build a warehouse for $950,000 on March 30, 2018 with a performance bonus of $50,000 if the building is completed by July 31, 2018. The bonus is reduced by $10,000 each week that completion is delayed. Marle commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:

Completed by Probability
31-Jul-18 65%
7-Aug-18 25%
14-Aug-18 5%
21-Aug-18 5%

Required:
Determine the amount of the transaction price.


Sagot :

Answer:

$995,000

Explanation:

The computation of the amount of the transaction price is shown below;

July 31, 2018 ($950,000+$50,000) × 0.65 =  $650,000

August 7, 2018  ($950,000+$40,000) × 0.25 = $247,500

August 14, 2018 ($950,000 + $30,000) × .05 = $49,000

August 21, 2018 ($950,000 + $20,000) × .05 = $48,500

Total $995,000

In this way it should be calculated