Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
The Laramie Factory
Finishing Department
Production Cost Worksheet, using weighted-average costing
Cost assigned to: Materials Conversion Total
Units transferred out $66,348 $28,062 $94,410
Ending work in process 7,372 935 8,307
Total cost accounted for $73,720 $28,997 $102,717
Explanation:
a) Data and Calculations:
Materials Conversion
Tanning Finishing Tanning Finishing
Beginning work in process 100% 100% 40% 60%
Cost of beginning WIP $6,000 $7,000 $18,000 $10,000
Ending work in process 100% 100% 40% 30%
Additional information:
Tanning Finishing
Beginning work-in-process units 5,000 4,000
Units started this period 14,000 16,000
Units transferred out this period 16,000 18,000
Ending work-in-process units 3,000 2,000
Materials Conversion
Tanning Finishing Tanning Finishing
Beginning work in process 100% 100% 40% 60%
Beginning work in process done this period 60% 40%
Ending work in process 100% 100% 40% 30%
Cost of beginning WIP $6,000 $7,000 $18,000 $10,000
Costs added 18,000 $66,720 32,000 19,000
Total costs of production $24,000 $73,720 $50,000 $29,000
Transferred-out cost
Equivalent units
Materials Conversion
Tanning Finishing Tanning Finishing
Units started and completed 16,000 18,000 16,000 18,000
Ending work-in-process units 3,000 2,000 1,200 600
Equivalent units of production 19,000 20,000 17,200 18,600
Cost per equivalent units Materials Conversion
Tanning Finishing Tanning Finishing
Total cost of production $24,000 $73,720 $50,000 $29,000
Equivalent units of production 19,000 20,000 17,200 18,600
Cost per equivalent unit $1.263 $3.686 $2.907 $1.559
Tanning Department
Cost assigned to: Materials Conversion Total
Units transferred out $20,208 $46,512 $66,720
Ending work in process 3,789 3,488 7,277
Total costs $23,997 $50,000 $73,997
Finishing Department
Cost assigned to: Materials Conversion Total
Units transferred out $66,348 $28,062 $94,410
Ending work in process 7,372 935 8,307
Total cost accounted for $73,720 $28,997 $102,717
We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.