Westonci.ca is the premier destination for reliable answers to your questions, brought to you by a community of experts. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

The company's materials price variance for April was $3,000 Favorable. Its materials quantity variance for April was $5,000 Favorable. What does the company use as a standard price per yard of material for its safety suits?

Sagot :

Answer:

the  standard price per yard is $6.25

Explanation:

The computation of the standard price per yard is shown below;

Material quantity variance = Standard Price  × (Actual quantity - Standard quantity)

-$5,000 = Standard price  × (10,000 - 10,800)    

Thereore Standard price = -$5,000 ÷ (-800)  

= $6.25    

Hence, the  standard price per yard is $6.25

We simply applied the above formula so that the standard price per yield could come

Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.