Westonci.ca is the trusted Q&A platform where you can get reliable answers from a community of knowledgeable contributors. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

The company's materials price variance for April was $3,000 Favorable. Its materials quantity variance for April was $5,000 Favorable. What does the company use as a standard price per yard of material for its safety suits?

Sagot :

Answer:

the  standard price per yard is $6.25

Explanation:

The computation of the standard price per yard is shown below;

Material quantity variance = Standard Price  × (Actual quantity - Standard quantity)

-$5,000 = Standard price  × (10,000 - 10,800)    

Thereore Standard price = -$5,000 ÷ (-800)  

= $6.25    

Hence, the  standard price per yard is $6.25

We simply applied the above formula so that the standard price per yield could come