At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer:
Windhoek Mines, Ltd.
The net present value of the proposed mining project is:
= ($232,950).
Explanation:
a) Data and Calculations:
Cost of new equipment and timbers = $500,000
Working capital required = $100,000
Annual net cash receipts = $120,000
Cost to construct new roads in three years = $40,000
Salvage value of equipment in four years = $65,000
Estimated useful life of mine = 4 years
Working capital released in four years = $100,000
Required rate of return = 20%
Cash Flows PV factor Present Value
Cost of new equipment and timbers $500,000 1 -$500,000
Working capital required 100,000 1 -100,000
Annual net cash receipts 120,000 2.589 310,680
Cost to construct new roads in 3 years 40,000 0.579 -23,160
Salvage value of equipment in 4 years 65,000 0.482 31,330
Working capital released in 4 years 100,000 0.482 48,200
Net present value ($232,950)
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Get the answers you need at Westonci.ca. Stay informed by returning for our latest expert advice.