Welcome to Westonci.ca, where your questions are met with accurate answers from a community of experts and enthusiasts. Join our Q&A platform to get precise answers from experts in diverse fields and enhance your understanding. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
a.
VC/unit = $3 per unit
Fixed Cost = $800
b.
Total Cost = $25400
Explanation:
a.
The high-low method is used to separate the components of a mixed cost and it calculates the variable cost component in a mixed cost. The formula to calculate the variable cost per unit under the high-low method is as follows,
VC/unit = [Highest Activity cost - Lowest Activity Cost] / [Highest Activity units - Lowest Activity units]
VC/unit = [22400 - 6500] / [7200 - 1900]
VC/unit = $3 per unit
Using figures from March, The total fixed costs will be,
Fixed cost = 6500 - [3 * 1900]
Fixed Cost = $800
b.
Total cost in a month with 8200 units will be,
Total Cost = Total Fixed cost + Total variable costs
Total Cost = 800 + (3 * 8200)
Total Cost = $25400
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.