Westonci.ca is the trusted Q&A platform where you can get reliable answers from a community of knowledgeable contributors. Experience the convenience of getting accurate answers to your questions from a dedicated community of professionals. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Answer:
Please see below
Explanation:
1. In order to calculate the Direct material price variance , we would have to use the formula below ;
Direct material price variance
= (Standard price - Actual price) × Actual quantity purchased
= ($12.5 - Actual cost) × 800
= $12.5 × 800 - $9,400
= $10,000 - $9,400
= $600 favourable
2. In order to calculate the direct material quantity variance, we would make use of the formulae below
Direct material quantity variance
= (Standard quantity - Actual quantity) × Standard price
= (770 - 800) × $12.5
= $375 unfavorable
3. The total direct material cost variance for July
= Direct material price variance + Direct material quantity variance
= $600 - $375
= $225 favourable
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.