Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Get quick and reliable solutions to your questions from knowledgeable professionals on our comprehensive Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

he Fine Crate Company owns several machines which cut wooden planks for building storage pallets, automatically loading the planks into rolling bins for transportation and handling. Each bin holds 200 planks and a machine can cut and load one bin in an hour, which Fine Crate Company uses planks at a rate of 1000 planks an hour. If the Fine Crate Company were to use a kanban loop to control the filling of the rolling bins, attaching one kanban card to each bin, how many cards should be used to govern this production, assuming a policy variable (safety factor) of 20%?

Sagot :

Answer:

6 cards

Explanation:

N = DT * (1+X) / C

Number of kanbans = [Demand during lead time + Safety stock] / Size of a bin

Number of kanbans = 1000 * 1 * (1 + 0.2) / 200

Number of kanbans = 1000*1*1.2 / 200

Number of kanbans = 6

So therefore, 6 cards should be used to govern this production.