At Westonci.ca, we connect you with experts who provide detailed answers to your most pressing questions. Start exploring now! Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
Results are below.
Explanation:
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (5 - 4.95)*14,000
Direct material price variance= $700 favorable
Actual price= 69,300 / 14,000= $4.95
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (9*1,500 - 14,000)*5
Direct material quantity variance= Â $2,500 unfavorable
To calculate the direct labor rate and efficiency variance, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (5*1,500 - 7,600)*10
Direct labor time (efficiency) variance= $1,000 unfavorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (10 - 10.6)*7,600
Direct labor rate variance= $4,560 unfavorable
Actual rate= 80,560 / 7,600= $10.6
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.