Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Discover solutions to your questions from experienced professionals across multiple fields on our comprehensive Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer:
Results are below.
Explanation:
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (5 - 4.95)*14,000
Direct material price variance= $700 favorable
Actual price= 69,300 / 14,000= $4.95
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (9*1,500 - 14,000)*5
Direct material quantity variance= $2,500 unfavorable
To calculate the direct labor rate and efficiency variance, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (5*1,500 - 7,600)*10
Direct labor time (efficiency) variance= $1,000 unfavorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (10 - 10.6)*7,600
Direct labor rate variance= $4,560 unfavorable
Actual rate= 80,560 / 7,600= $10.6
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.