Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

A project requires a cost in Year O (right now) of $7M. The project will then provide a revenue of $3M per year for Years 1-3. Your discount rate is 15%. The NPV of the project is: Between 0 and $1M Less than zero Between $1M and $2M O More than $2M

A Project Requires A Cost In Year O Right Now Of 7M The Project Will Then Provide A Revenue Of 3M Per Year For Years 13 Your Discount Rate Is 15 The NPV Of The class=

Sagot :

Answer: Less than zero

Explanation:

Based on the information given, the NPV of the project will be calculated as the present value of cash flow earned minus the initial expenditure.

The present value of cash flow will be:

= 3/(1 + 15%)¹ + 3/(1 + 15%)² + 3/(1 + 15%)³

= 3/(1.15)1 + 3/(1.15)² + 3/(1.15)³

= 3/1.15 + 3/1.3225 + 3/1.520875

= 2.61 + 2.27 + 1.98

= $6.86 million

Then NPV will be:

= $6.86 million - $7 million

= -$1.14 million

Therefore, the correct option is "less than zero".