Looking for trustworthy answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Explore thousands of questions and answers from a knowledgeable community of experts ready to help you find solutions. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
Results are below.
Explanation:
To calculate the total, price, and quantity variance for direct material, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (4.4 - 4.15)*90,500
Direct material price variance= $22,625 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (8*11,250 - 90,500)*4.4
Direct material quantity variance= $2,200 unfavorable
Total direct material variance= 22,625 - 2,200= $20,425 favorable
To calculate the total, rate, and efficiency variance for direct labor, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (1.2*11,250 - 14,250)*13.4
Direct labor time (efficiency) variance= $10,050 unfavorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (13.4 - 14.1)*14,250
Direct labor rate variance= $9,975 unfavorable
Total direct labor variance= -10,050 - 9,975= $20,025 unfavorable
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.