Westonci.ca offers fast, accurate answers to your questions. Join our community and get the insights you need now. Explore thousands of questions and answers from a knowledgeable community of experts on our user-friendly platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer:
Results are below.
Explanation:
To calculate the total, price, and quantity variance for direct material, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (4.4 - 4.15)*90,500
Direct material price variance= $22,625 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (8*11,250 - 90,500)*4.4
Direct material quantity variance= $2,200 unfavorable
Total direct material variance= 22,625 - 2,200= $20,425 favorable
To calculate the total, rate, and efficiency variance for direct labor, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (1.2*11,250 - 14,250)*13.4
Direct labor time (efficiency) variance= $10,050 unfavorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (13.4 - 14.1)*14,250
Direct labor rate variance= $9,975 unfavorable
Total direct labor variance= -10,050 - 9,975= $20,025 unfavorable
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.