Looking for reliable answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

projects variable labor costs of $21,500 in March when 8,600 units are produced. If production is expected to drop to 8,000 units in April, what is the expected labor cost in April

Sagot :

Answer:

Total direct labor cost=$20,000

Explanation:

First, we need to calculate the direct labor cost per unit:

Direct labor cost per unit= total cost / number of units

Direct labor cost per unit= 21,500 / 8,600

Direct labor cost per unit= $2.5

Now, the total cost for 8,000 units:

Total direct labor cost= 2.5*8,000

Total direct labor cost=$20,000

We appreciate your time on our site. Don't hesitate to return whenever you have more questions or need further clarification. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Get the answers you need at Westonci.ca. Stay informed by returning for our latest expert advice.