Welcome to Westonci.ca, your go-to destination for finding answers to all your questions. Join our expert community today! Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.
Sagot :
Answer:
the direct labor cost budgeted is $1,500,000
Explanation:
The computation of the direct labor cost budgeted is given below:
The Direct labor budget for September is
= September production × required no of hours × direct labor wage per hour
= 50,000 × 2hour × $15
= $1,500,000
hence, the direct labor cost budgeted is $1,500,000
Thank you for choosing our service. We're dedicated to providing the best answers for all your questions. Visit us again. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.