Discover the answers you need at Westonci.ca, where experts provide clear and concise information on various topics. Discover comprehensive solutions to your questions from a wide network of experts on our user-friendly platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time

Sagot :

Answer:

9

Explanation:

Given that

There is five stations who have the process time of 5,9,4,9 and 8

We need to find out the bottleneck time

so, as we know that the bottleneck is the duration of the activity who have longer time

So as per the given situation the 9 has the longest duration activity time

So, the same is to be considered