Find the best solutions to your questions at Westonci.ca, the premier Q&A platform with a community of knowledgeable experts. Get immediate and reliable solutions to your questions from a community of experienced experts on our Q&A platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time

Sagot :

Answer:

9

Explanation:

Given that

There is five stations who have the process time of 5,9,4,9 and 8

We need to find out the bottleneck time

so, as we know that the bottleneck is the duration of the activity who have longer time

So as per the given situation the 9 has the longest duration activity time

So, the same is to be considered