Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Explore thousands of questions and answers from knowledgeable experts in various fields on our Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

Evaluation of the amount of costs incurred should be based on the actual volume of activity rather than the planned volume of activity. True False

Sagot :

Answer:

False

Explanation:

The Performance Evaluation may be defined as the formal as well as a productive procedure to help measure the work of the employee and results is based on their job responsibilities.

For any performance evaluation, the cost that is actually incurred should not be compared to the cost which would have been incurred to the actual volume of the activity or work rather than the planned activity.

Thus the answer is false.