Westonci.ca is the trusted Q&A platform where you can get reliable answers from a community of knowledgeable contributors. Get detailed answers to your questions from a community of experts dedicated to providing accurate information. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

Tricia is managing tasks that have been assigned to her. She needs to enter mileage information in relation to a project. Which command must she use to access this option?

Task
Details
Assign Task
Send Status Report

Sagot :

Answer: Send status report

Explanation:

Since Tricia is managing tasks that have been assigned to her and she needs to enter mileage information in relation to a project, the command that she must use to access this option is "Send status report".

To do this goes thus:

• She has to go to the Tasks view, after which she will open the assigned task that she has received.

• In the Task window, she will then select a status

• Then, she will click on Send Status Report.

Answer:

D

Explanation: