Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Get expert answers to your questions quickly and accurately from our dedicated community of professionals. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

Mariott Condominium, located near San Diego, California, plans to renovate its main building. The project will begin April 1, and the goal is to complete by August 1 (in 17 weeks). The condominium manager identifed the renovation activities and their estimated time below.
a) Draw a project network. You may want to draw on paper then do it here by connecting the given nodes with arcs (i.e, arrows). You might not use all of the given arcs.
b) What are the critical activities?
c) What activity has the most slack time?
d) Will the project be completed by August 1?


Sagot :

Answer:

7

Explanation:

because

We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.