Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

If a process step has a LARGE setup time and a SMALL pure-processing time per unit, what batch size will result in the fastest completion of ALL of the units at this step? Assume there is only ONE resource at this step.

Sagot :

Answer:

A large batch

Explanation:

Batch processing is used by large businesses to automate production process in such a way that efficiency is achieved in the shortest time.

This requires processing of a set of products as opposed to individual transactions.

In the given scenario where a process step has a large setup time and a small pure-processing time per unit, it means that the time to set up the production process is much while the individual processing time per product is small.

A large batch will be best in this situation because once it is set up more product will be processed at once.

However if smaller batch was used the setup time will reoccur often and slow down the process.

Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.