Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

PLS HELP ASAP
It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electricians take to do the same job?


Sagot :

pretty sure it’s 27 :)

Answer: The 32 electricians are expected to finish the job in 27 days.

Step-by-step explanation:

Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.