Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Explore in-depth answers to your questions from a knowledgeable community of experts across different fields. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
Answer:
The number of men needed to perform a piece of work twice as great in tenth part of the time working 8 hours a day supposing that three of the second set can do as much work as four of the first set is:
- 1200 men.
Step-by-step explanation:
To find the answer, first, we're gonna find how many hours take to make the piece of work in 16 days, taking into account each day just has 10 hours:
- Number of hours to make a piece of work = 16 * 10 hours
- Number of hours to make a piece of work = 160 hours.
Now, we divide the total hours among the number of persons:
- Equivalence of hours per person = 160 hours / 80 persons.
- Equivalence of hours per person = 2 hours /person
This equivalence isn't the real work of each person, we only need this value to make the next calculations. Now, we have a piece of work twice as great as the first, then, we can calculate the hours the piece of work needs to perform it (twice!):
- Number of hours to make the second piece of work = 160 hours * 2
- Number of hours to make the second piece of work = 320 hours
We need to make this work in tenth part of the time working 8 hours a day, it means:
- Time used to the second work = 320 hours / 10
- Time used to the second work = 32 hours
- Time used to the second work = 32 hours / 8 hours (as each day has 8 hours)
- Time used to the second work = 4 days
Now, we know three of the second set can do as much work as four of the first set, taking into account the calculated equivalence, we have:
- Work of four workers of first set = Work of three workers of second set
- Work of four workers of first set = Equivalence * 4 persons.
- Work of four workers of first set = 2 hours /person * 4 persons
- Work of four workers of first set = 8 hours.
So, three persons of the second set can make a equivalence of 8 hours. At last, we calculate all the number of workers we need in a regular time:
- Number of needed workers in a regular time = (320 hours / 8 hours) * 3 persons.
- Number of needed workers in a regular time = 40 * 3 persons
- Number of needed workers in a regular time = 120 persons
Remember we need to perform the job not in a regular time, we need to perform it in tenth part of the time, by this reason, we need 10 times the number of people:
- Number of needed workers in tenth part of the time = 120 persons * 10
- Number of needed workers in tenth part of the time = 1200 persons
With this calculations, you can find the number of men needed to perform a piece of work twice as great in tenth part of the time working 8 hours a day supposing that three of the second set can do as much work as four of the first set is 1200 persons.
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for choosing Westonci.ca as your information source. We look forward to your next visit.